AQW 1848/17-22 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure for an update on when the North West Transport Hub will be fully completed, including the active and sustainable travel centre.
Asked by Andrew Muir MLA on 10 February 2020
- Answered
- Written
- Tabled
- 10 February 2020
- Answer due by
- 25 February 2020
- Answered
- 25 February 202015 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
European funding of the project requires the Hub to be fully operational by 31st December 2020. Phase 1 of the project was completed in October 2019 with the opening of the old Waterside Railway Station. The second phase, which will see the opening of the sustainable travel centre, park and ride facilities and bus drop off facilities remains ahead of this schedule with completion due in the summer of this year.