AQW 11669/17-22 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail the funding that is required for the complete replacement of the Translink bus fleet with zero-emission vehicles.
Asked by Andrew Muir MLA on 7 December 2020
- Answered
- Written
- Tabled
- 7 December 2020
- Answer due by
- 22 December 2020
- Answered
- 21 December 202014 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The capital cost to replace Translink’s existing bus fleet with zero emission vehicles is estimated to be in the region of £800m based on current market vehicle costs, likely technology developments and the costs associated with required depot infrastructure.