AQW 16318/17-22 Written question to the Minister of Education
To ask the Minister of Education for an update on the progress of the St Patrick’s Primary School, Holywood new build construction project
Asked by Andrew Muir MLA on 12 March 2021
- Answered
- Written
- Tabled
- 12 March 2021
- Answer due by
- 30 March 2021
- Answered
- 23 March 202111 days after tabling
- Department
- Department of Education
- Priority question
- No
Answer
St Patrick’s Primary School, Holywood, has not been announced for major capital investment, therefore, there are no plans for a new build construction project being advanced for this school at this time.