AQW 19373/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on the compilation of the feasibility study for Phase 3 Derry-Londonderry to Coleraine rail line upgrade.

Asked by Andrew Muir MLA on 24 May 2021

  • Answered
  • Written
Tabled
24 May 2021
Answer due by
9 June 2021
Answered
28 May 20214 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

Work on the feasibility study is ongoing with a number of topographical and pilot studies underway and the report is still on schedule to be completed by November 2021. A full business case will then be prepared and submitted to me in spring 2022. This will ensure that all future spend is fully informed by a robust business case and that there is high-level assurance on costs and on risk and benefit realisation.