AQW 20559/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on timescales concerning the review of the implementation of the Planning Act (NI) 2011.

Asked by Andrew Muir MLA on 17 June 2021

  • Answered
  • Written
  • Priority
Tabled
17 June 2021
Answer due by
24 June 2021
Answered
23 June 20216 days after tabling
Department
Department for Infrastructure
Priority question
Yes

Answer

As you are aware my Department issued a Call for Evidence to targeted stakeholders which closed on 16 April 2021. This attracted 55 responses from a diverse range of stakeholders including, all 11 local councils, professional bodies, electricity/renewables and business sectors, environmental NGOs, community and housing interests, academia and several political parties. My officials are currently assessing these responses, some of which are long, complex and detailed. As careful consideration will need to be given to the issues which have emerged from the Call for Evidence, this will obviously take time.

I will then give careful consideration to the responses to determine whether any suggested amendment, retention or repeal of associated provisions would assist in better achieving the objectives of the 2011 Planning Act. In addition, it will be necessary to determine whether changes (if implemented) would require amendment to primary and/or subordinate legislation, or could be effected through guidance or other means.

I anticipate that the associated review report will be published later this year.