AQW 1906/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure to detail how many scheduled roads resurfacing projects in North Down, which were included in his Department's 2021/22 Annual Report, have not been completed due to the legal challenge of the asphalt resurfacing contract competition.

Asked by Andrew Muir MLA on 21 June 2022

  • Answered
  • Written
Tabled
21 June 2022
Answer due by
6 July 2022
Answered
29 June 20228 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

Five schemes in the planned programme for 2021/22 were not completed prior to the expiry of the asphalt resurfacing contract in November 2021 at: Hawthorne Drive, Bangor; Beechwood Avenue, Bangor; Beechwood Gardens, Bangor; Silverstream Drive, Bangor; and Kinnegar Drive, Holywood.

Should you have any further questions on this matter, please contact DfI Roads Southern Division at: dfiroads.southern@infrastructure-ni.gov.uk.