AQW 1906/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail how many scheduled roads resurfacing projects in North Down, which were included in his Department's 2021/22 Annual Report, have not been completed due to the legal challenge of the asphalt resurfacing contract competition.
Asked by Andrew Muir MLA on 21 June 2022
- Answered
- Written
- Tabled
- 21 June 2022
- Answer due by
- 6 July 2022
- Answered
- 29 June 20228 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
Five schemes in the planned programme for 2021/22 were not completed prior to the expiry of the asphalt resurfacing contract in November 2021 at: Hawthorne Drive, Bangor; Beechwood Avenue, Bangor; Beechwood Gardens, Bangor; Silverstream Drive, Bangor; and Kinnegar Drive, Holywood.
Should you have any further questions on this matter, please contact DfI Roads Southern Division at: dfiroads.southern@infrastructure-ni.gov.uk.