AQW 7388/17-22 Written question to the Minister of Finance

To ask the Minister of Finance what progress has been made on implementing the recommendations of the 2019 Northern Ireland Audit Office report on Major Capital Projects.

Asked by Andrew Muir MLA on 22 September 2020

  • Answered
  • Written
Tabled
22 September 2020
Answer due by
7 October 2020
Answered
6 October 202014 days after tabling
Department
Department of Finance
Priority question
No

Answer

The Northern Ireland Audit Office report on Major Capital Projects from December 2019 is the subject of a Public Accounts Committee (PAC) enquiry which commenced in March 2020.

It is normal practice to wait for PAC to publish its recommendations so as not to pre-empt the outcome of the enquiry. When the PAC recommendations are published, I will ensure that any recommendations, on the role of procurement in the delivery of major capital projects, are taken up by the Procurement Board.

Official sources