AQW 16320/17-22 Written question to the Minister of Education

To ask the Minister of Education for an update on the progress of the Crawfordsburn Primary School new build construction project.

Asked by Andrew Muir MLA on 12 March 2021

  • Answered
  • Written
Tabled
12 March 2021
Answer due by
30 March 2021
Answered
19 March 20217 days after tabling
Department
Department of Education
Priority question
No

Answer

The major capital investment project to provide suitable accommodation for an 8 class base primary school for Crawfordsburn Primary School is progressing well.

The Integrated Consultancy Team (Design Team), Isherwood & Ellis LLP, appointed in October 2019, is currently finalising the RIBA Stage 3 (Developed Design) which is due for submission to my Department’s technical advisors in April 2021.