AQW 17433/17-22 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail (i) the cycle routes delivered under road improvement and resurfacing schemes by Roads Southern Division in each of the last five years; and (ii) a summary of the number of schemes and length broken down by facility type as defined in departmental guidance "Measures to regulate traffic RSPPG E063" (a) totally separate facility; (b) cycle lane on the carriageway; and (c) share walking/cycling facility.
Asked by Andrew Muir MLA on 15 April 2021
- Answered
- Written
- Tabled
- 15 April 2021
- Answer due by
- 30 April 2021
- Answered
- 23 April 20218 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
Details of the cycling facilities that have been constructed by my Department within Southern Division in the previous 5 years, by facility type, are provided in the following table:
| Year | Scheme Name | Type of cycling facility provided | Length (KM) |
| 2016/17 | N/A | N/A | |
| 2017/18 | Monaghan Road, Armagh | New toucan crossing | - |
| 2018/19 | Moy Road, Scotch Street, Portadown | New toucan crossing | - |
| Carbane Way | New toucan crossing | - | |
| Shepherds Way | New toucan crossing | - | |
| Carnbane Way / Shepherds Way | Shared walking/cycling provision | 1.69 | |
| 2019/20 | A2 Belfast Road, Bangor (At Ballygilbert) | Shared walking/cycling provision | 0.50 |
| 2020/21 | Newtownards Traffic Study | Shared walking/cycling provision | Ongoing |
| Nursery Road, Armagh | Shared walking/cycling provision | 0.340 | |
| Total length (KM) | 2.53 |
Details of these schemes are readily available in the reports presented to Council each year which are available at: