AQW 28868/17-22 Written question to the Minister for Communities
To ask the Minister for Communities for a breakdown of (i) capital; and (ii) resource expenditure incurred by her Department on the Queen’s Parade development, Bangor, since her Department, and the legacy departments, became involved.
Asked by Andrew Muir MLA on 27 January 2022
- Answered
- Written
- After due date
- Tabled
- 27 January 2022
- Answer due by
- 11 February 2022
- Answered
- 16 February 202220 days after tabling
- Department
- Department for Communities
- Priority question
- No
Answer
My Department has spent a total of £10.27m in site acquisition and maintenance on the Queen’s Parade project.
This can be broken down as follows:
Capital expenditure of £8.81m; and
Resource expenditure of £1.46m (up to 31st December 2021)