AQW 4223/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to outline the planned spend during the current and future financial years on the York Street Interchange Scheme.
Asked by Andrew Muir MLA on 6 October 2022
- Answered
- Written
- Tabled
- 6 October 2022
- Answer due by
- 21 October 2022
- Answered
- 21 October 202215 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
In the absence of an Executive, budgets have not been agreed for the 2022-23 financial year or future years. However, to ensure that my Department continues to develop and deliver much needed investment in our infrastructure, I agreed capital allocations for 2022-23 which include £1.4m for the on-going development of the York Street Interchange project.
Future funding will be dependent on Executive priorities and associated budget settlements.