AQW 4302/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure to detail the specific timescale for delivery of a controlled crossing at East Circular Road, Bangor, near St Columbanus' College.

Asked by Andrew Muir MLA on 7 October 2022

  • Answered
  • Written
Tabled
7 October 2022
Answer due by
24 October 2022
Answered
24 October 202217 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

Local officials have confirmed that a controlled pedestrian crossing, which will improve road safety for pedestrians crossing this heavily trafficked A Class road, is included within a programme of works for this financial year. Timescales for delivery of this scheme will be dependent on the availability of contractor resources.

Should you have any further questions on this matter, please contact DfI Roads Southern Division at: dfiroads.southern@infrastructure-ni.gov.uk

Official sources